Business and finance: how much is the expected total variable cost on the August budget?

Aaron’s chairs is in the process of preparing a production cost budget for August. Actual costs in July for 120 chairs were:

Materials cost $4,540
Labor cost 2,740
Rent 1,500
Depreciation 2,500
Other fixed costs

3,200

Materials and labor are the only variable costs. If production and sales are budgeted to increase to 130 chairs in August, how much is the expected total variable cost on the August budget?